Royal Decree 1032/2026, of 20 November, was published in Spain's official gazette (BOE) number 290 on the 21st and came into force on the 22nd. Every headline we have read stopped at the same sentence: 80% renewables, hour by hour, for data centres of 10 MW and above. That threshold is real and it sits in article 2.1. What no headline mentions is how the sentence opens: "Without prejudice to the provisions of paragraph 3 and article 5…". Article 5 is expressly carved out of the power threshold, and the preamble repeats it plainly: "Article 5 applies, by contrast, regardless of access power." That article is not about energy: it is about where your data may sit and from where somebody may type on the machine holding it.

Back in August we read the whole draft and published two readings: that the number actually filtering projects was not the 80% but a PUE of 1.15, and that the word "resilience" was in the title and not in the articles. There is an approved text now, so both deserve checking: one has been postponed and the other still stands, with a caveat we ourselves had conceded back in September.

What article 5 says, and who it says it to

Article 5 is titled "Digital sovereignty requirements" and applies to data centres hosting HIGH-category information systems under annex I of Royal Decree 311/2022, Spain's National Security Framework —systems handling classified information are excluded—. It does not ask for megawatts: it asks what you host. Its three conditions, in paragraph 2, are these.

a) "The content data of those systems and the data derived from use of the service […] may not be processed, stored or transferred outside the European Union or the European Economic Area, except where a European Union rule establishes, for those systems or data, an equivalent or alternative regime of protection and transfer."

b) "The obligated party must have, within the European Union or the European Economic Area, the staff and material means required to deliver the hosting service and to comply with this article." And, verbatim: "Administration, support or maintenance operations may only be carried out from other countries where they are technically indispensable and are limited to the actions and the time strictly necessary," recording the operation and the identity of whoever performs it. Remote access to that data is allowed, as an exception to point a), where strictly necessary and without leaving persistent copies outside the European Economic Area. "The record shall be kept for at least five years, available to the Ministry for Digital Transformation and the Civil Service."

c) "Appropriate and proportionate legal, technical and organisational measures shall be adopted against access requests […] made by third-country authorities that are contrary to European Union law or to national law and are not covered by an applicable international agreement in force."

Two details inside article 5 change who owns the problem. The first: "For the purposes of this article, the obligated party shall be the owner of the data centre." The signature belongs to the owner of the room, not the owner of the system. The second is the switch: "The conditions in paragraph 2 shall not be enforceable with respect to a data centre's systems until the obligated party is notified that one of its systems is HIGH-category." The obligation does not switch on with the law: it switches on with a notification.

The paperwork enters through the electricity permit, and whoever reviews it sits elsewhere

Here is, in our judgement, the most interesting thing in the decree, and a piece of legal engineering worth looking at closely. Article 5.4 reads: "Together with the application for access and connection permits, the obligated party shall file a responsible declaration with the grid operator," stating either that it hosts no HIGH-category systems or that it complies with the paragraph 2 conditions; and it adds that "this declaration must be filed simultaneously with the Ministry for Digital Transformation and the Civil Service." Article 4.1 makes the granting of the permit conditional on, among other things, "the filing of the responsible declaration regarding the digital sovereignty requirements provided for in article 5.4." And 5.5 asks for a second declaration, to the Ministry, before you start hosting one of those systems.

In other words: the procedure that forces you to say it is the one for the power feed, but the grid operator only checks that the paper is there. The one who can look inside is the Ministry, and article 5.6 lets it request information, order checks, demand that you fix things and —this is the sentence that matters— report breaches "to the public-sector entities responsible for the affected systems, so that they may adopt the measures appropriate under Royal Decree 311/2022 […] and under the corresponding contracts." Translated: this does not end with anyone's power being cut. It ends in the contract your public client has signed with you.

From draft to law: what moved

Here is what we wrote in August about the draft, set against what the published text says. No touch-ups.

What we read in the draft (27 Aug) What the approved text says
The decree applied from 1 MW of access power (that is how we reported it in September) The threshold rises to 10 MW, or groups at the same site under the same ownership adding up to it. This is the single biggest change, and it leaves out almost every mid-sized room in the country.
The number that filters projects is a PUE ≤ 1.15 and a WUE ≤ 0.1 The 1.15 is still there, but with a date: the second transitional provision requires it of centres entering service from 1 January 2030, and article 6.1 keeps class "A" as the permanent bar. Until then a transitional 1.25 applies. Our number did not move: it was postponed.
Surcharges of up to 500% on network tolls and charges (article 10 of the draft) "500%" does not appear in the text. Article 10 is now "Penalty regime" and the money lives in article 9: compensations of €6 to €25 per MWh (additionality) and €2 to €16 per MWh (hourly correlation).
Article 5.2 leaves part of what is yours outside the sovereignty claim The approved text closes that gap: only "metadata relating to the technical management of the service" is excluded, and content data remains content data "even where it is incorporated, wholly or in part, into activity logs, metadata or telemetry […]. Encrypting it shall not alter that status." Here it is us who were corrected.
"Resilience" is in the title and not in the articles (with the caveat, which we flagged at the time, of the first final provision) Unchanged, and then some: of the 13 articles none regulates redundancy, continuity or availability, and article 5 —titled "Resilience and digital sovereignty requirements" in the draft— lost the word along the way. The first final provision does keep it as a criterion in capacity auctions.

The PUE sentence is worth reading in full, because the version going round is cropped. The preamble says: "On a transitional basis, and until the European labelling scheme applies, expected in August 2027, maximum values of PUE of 1.25 and WUE of 0.1 are set." That is the preamble, not the articles; the operative deadlines sit in the sixth and eighth transitional provisions, and the latter lets anyone with a grid access contract predating 2029 keep the 1.25 until 31 December 2031. And the slack, while it lasts, is larger than it looks: PUE is total consumption divided by IT consumption, so what loosens is the non-IT spend, which goes from being allowed 15% of the IT load to being allowed 25%. That is not 8.7% more room for cooling, losses and climate: it is two thirds more. That is our arithmetic, not a quotation. What does not change is the destination: class "A" in article 6.1 and the 1.15 from 2030 are both still written down.

What deviating costs now, with a price list

Article 9 sets out two scales. For additionality —covering less than 80% of annual consumption with new renewable generation—: €25/MWh below 20% coverage, €19/MWh between 20 and 40%, €12/MWh between 40 and 60%, and €6/MWh between 60 and 80%. For hourly correlation: €2/MWh if you deviate by less than 5%, then 5, 8, 11 and €16/MWh as you climb to 50% or more. The final settlement is approved by the Secretary of State for Energy "before 31 March each year."

For scale: a centre with exactly 10 MW of access power drawing all of it across the 8,760 hours of the year would move 87,600 MWh. At the worst additionality bracket that is €2.19 million a year, and at the worst correlation bracket another €1.40 million. The two scales stack: €3.59 million a year. Nobody draws 100% of their access power all year, and article 7.6 also caps consumption at whatever additionality can certify, so that worst case is not merely improbable, it is unsustainable: the figure is an upper bound, not an invoice. But it shows the change of nature: the draft threatened a multiplier on network tolls that cannot be modelled; the approved text sets a price per megawatt-hour. A risk you cannot compute stops investment. A price, by contrast, goes into the spreadsheet and you decide whether it is worth it. We think that difference is enormous, and that it is why this part stopped being frightening.

Which obligation, which threshold, who answers

Article What it asks for Threshold
5 Data in the EU/EEA, staff and material means in the EU/EEA, administration from third countries only where technically indispensable and with a five-year log No power threshold. Hosting an ENS HIGH-category system, from the moment you are notified
6 a 9 Class "A" for energy and water efficiency (article 6.1), with a transitional 1.25 while the European labelling scheme does not yet apply; 80% annual additionality; 80% hour-by-hour correlation; compensation for deviations Access power ≥ 10 MW (or groups at the same site and under the same ownership adding up to it)
13 Publish the indicators in annexes I and II of Delegated Regulation (EU) 2024/1364, each year before 15 May IT power ≥ 500 kW, regardless of access power. From 1 MW of IT there is also a second annual filing, on the European code of conduct (article 13.5)
4 A responsible declaration on digital sovereignty filed with the grid operator, as a condition for the permit Anyone applying for access and connection permits

Why this reaches you even if you only rent three racks

You are not the obligated party: the owner of the centre is. If your infrastructure lives in colocation, the declaration they sign depends on a fact that lives inside your machines, and that they cannot see. If your software company runs a system for a public administration and that system is classified HIGH, the information has to travel from you up to the room. We expect to see that form turning up in contract renewals over the coming months, much as the renegotiation by kilowatts instead of rack units did in its day. What is worth having answered before it arrives:

  • Where the second copy lives. You know the primary site. Paragraph a)'s question is about the replica: if your backup leaves for a region outside the EEA, that is the problem, and it is not in the room, it is in your backup policy.
  • Who administers, and from where. If you have outsourced support with shifts outside the EEA, paragraph b) does not forbid it, but it demands that it be "technically indispensable", bounded in scope and time, and logged with identity. "It is cheaper for us" is not "technically indispensable".
  • Whether you keep that log for five years. A five-year record of remote access is not an operational log: it is an archive. In almost every shop we see, log retention expires long before that obligation does.
  • Which of your systems are classified HIGH. If you do not know, ask the public client: the category is set by the system owner, not by you and not by your hosting provider.

When this does NOT apply to you (and where our reading ends)

Three honest notes, because texts like this get used to sell fear and we would rather not. First: until you are notified that a system is HIGH-category, the paragraph 2 conditions are not enforceable; article 5.1 says so itself. Second, a correction aimed at ourselves: the metadata gap we pointed at in August has narrowed to "metadata relating to the technical management of the service", and article 3 shuts the door by adding that content data remains content data "even where it is incorporated, wholly or in part, into activity logs, metadata or telemetry" and that encrypting it "shall not alter that status." Anyone planning to sell through that gap no longer has one.

And third, which is where our reading ends: article 2.1 hooks the decree onto those who "have applied or are going to apply" for the access and connection permits of Royal Decree 1183/2020, including those holding a permit but not yet connected —who, incidentally, get twelve months from entry into force to adapt to article 5, under the fifth transitional provision—. An older centre, connected for years and with no live applications, fits that definition poorly. We are not lawyers and this is not legal advice: it is the exact question we would put to the provider —do you have any live access or connection applications?— because the answer decides whether the article 5 form lands on your desk at all.

In short

The decree postponed where the fighting was hardest —the PUE, which returns in 2030—, swapped a penalty nobody could compute for a price list, raised the threshold from 1 to 10 MW, and left untouched, with no megawatt threshold, the one article that is not about energy. If you host HIGH-category systems, the conversation of the coming months is not about renewables: it is about where your second copy lives and who has their hands on the keyboard at three in the morning. Those two questions are answered with an inventory, not with a declaration.

Sources (verified 24 Nov 2026): every quotation from the articles, the decree number, BOE number 290 of 21 November 2026 (pages 158186 to 158217), the 22 November entry into force, the €6–25/MWh and €2–16/MWh scales in article 9, the "before 31 March" settlement, the 500 kW threshold in article 2.3, the 15 May deadline in article 13, the reference to Delegated Regulation (EU) 2024/1364, the reference to annex I of Royal Decree 311/2022 and the list of 13 articles all come from the text of Royal Decree 1032/2026 as published in the BOE. The sentence about "maximum values of PUE of 1.25 and WUE of 0.1" sits in the preamble, not in the articles, and is preceded by "On a transitional basis, and until the European labelling scheme applies, expected in August 2027"; the PUE of 1.15 required of centres entering service from 1 January 2030 is in the second transitional provision, and the 1.25 windows are in the sixth and eighth. The twelve months to adapt to article 5 come from the fifth transitional provision, and the Ministry's follow-up control from article 5.6. Quotations in English are our translation: the official text exists only in Spanish. What we said about the 27 August draft is in our two posts from August and September, and can be checked word by word. Two corrections to our own draft of this post, caught in internal review before publishing: we had written that the 1.15 had disappeared from the text (it has not: it is postponed to 2030) and that sovereignty was checked by the grid operator (it is not: the operator checks that the declaration exists; the Ministry is the one that reviews it). What we do NOT claim: we do not say article 5 will apply to everyone —it depends on hosting an ENS HIGH-category system and on being notified— nor do we interpret the penalty regime in article 10, which refers out to other legislation and which we have not analysed here. The 87,600 MWh calculation, the €2.19 and €1.40 million figures and the reading of the PUE change as "two thirds more non-IT headroom" are our own arithmetic on the decree's numbers, and are flagged as such. This is technical analysis, not legal advice. Cover photo: Subestación eléctrica, Montilla by CFA1877 / Wikimedia Commons, CC BY-SA 4.0 (2,995 px wide), cropped and darkened by us. We chose it because the procedure where this decree actually gets enforced is the one for electricity grid access.

Could you answer today from where your system is administered?

At everyWAN we run our own hardware in a datacentre and provide 24x7 support from here, with the full name of whoever logs in. If the responsible-declaration form lands on your desk and you do not know what to answer, that is the conversation.

Talk to everyWAN

Tags:

Share:

Subscribe to our newsletter

To receive IT stories, everyWAN news and exclusive subscriber offers, sign up to our mailing list

Minorisa de Sistemas Informaticos y Gestión S.L. © 2026
everyWAN
everyWAN